Timing of initial works

15-29 April 2024

Phase one of the artwork will be installed over two weeks between 15 April – 29 April, with works occurring Monday to Friday between 7am and 5pm.

There will be some disruption to pedestrian access between Wright Street and Belmont Hub, including a four day closure of the ramp near the bus stop.

Public signage and detours, including accessible access, will be in place during the works.

There will be some disruption and noise while the artwork is being installed, we apologise for any inconvenience this may cause. The works are being planned to minimise the impact on Belmont Hub visitors and staff.

For more details contact the Arts & Place Team via artsandplace@belmont.wa.gov.au or 9477 7222.


Location of works - phase one

Areas around the entrance to Belmont Hub impacted by the works include:

  • planter box in front of Belmont Hub Wright Street Entrance
  • 8 Yolks café external seating
  • ramp from Wright Street bus stop to Belmont Hub (4 days)
  • a portion of the Wright Street bus stop seating area (4 days)

While the ramp between Wright Street and Belmont Hub is closed, pedestrians can access Belmont Hub via the ramp leading from the Civic Centre carpark to the Belmont Hub Library main entrance.


Timeline

  • Timeline item 1 - incomplete

    Phase 1 - 15-29 April

    • installation of artwork in planter,
    • sandblasting/staining the text onto planter box,
    • sandblasting/staining the artwork design onto the wall of the access ramp.
  • Timeline item 2 - incomplete

    Phase 2 - Timing TBC

    • Sandblasting design onto ground pavers (est. 3 days)